Monday 25 April 2011

Project Log Continued

Schedule: Week 15:

25/04/2011: Finish rendering out old man sequence 5 and old man sequence 6

26/04/2011: Showreel meeting (12 noon)/ work on promo showreel Intro and outro (deadline - wednesday 27th)

27/04/2011: showcase class meeting/ start final animation sequence (bully)

28/04/2011: Continue work on final animation sequence

29/04/2011: Continue work on final animation sequence

30/04/2011: Finish final animation sequence/ start to render out

01/05/2011: Finish rendering out sequence/ Start to put final piece together

02/05/2011: Finsh final piece - Narration and audio